A complete bill of materials with the quantity calculations behind each line — for budgeting, tendering or checking someone else's estimate.
Quick answer: A 100 point office typically needs around 17 boxes of 305 metre Cat6 cable, 100 keystone jacks plus 10 percent spares, five 24 port patch panels, 200 patch cords, a 42U rack, and containment sized for the full cable count with growth capacity. Cable is usually 10 to 15 percent of the total project cost; labour and containment dominate.
Most cabling estimates go wrong in the same two places: the point count is taken as the desk count, and the cable quantity is calculated from straight line distances. Both understate the job, and both surface as variations partway through installation.
This walkthrough uses a worked example — a single floor commercial office, 100 network points, one centrally positioned rack — and shows the arithmetic behind each line so you can substitute your own numbers.
The most common error at the outset. A 100 desk office does not need 100 network points.
Standard practice is two outlets per desk: one for the workstation, one spare for a phone, a printer, a dock or a future device. Adding cable during initial installation is cheap; adding it afterwards through a finished ceiling is not.
Then add the infrastructure points that are easy to forget:
• Wireless access points — roughly one per 1,000 square feet, ceiling mounted, PoE powered
• Network printers and multifunction devices
• IP cameras — entry points, corridors, server room
• Access control readers and door controllers
• Meeting room displays, video conferencing units and room booking panels
• Reception and visitor points
• Building management and HVAC controllers
A 100 desk office commonly lands between 220 and 250 points once these are counted. For this worked example we hold to 100 points so the arithmetic stays clear — but scale accordingly on a real project.
Work from the actual cable route, not the plan distance. The route includes the drop from the outlet up to the ceiling, the horizontal run through containment, the rise at the rack and the service loops at both ends. A 65 metre straight line commonly becomes a 90 metre route.
The calculation for 100 points:
|
Step |
Calculation |
Result |
|---|---|---|
|
Average run length |
Nearest + furthest ÷ 2 |
45 m |
|
Total cable |
100 × 45 |
4,500 m |
|
Wastage allowance |
+10% |
4,950 m |
|
Boxes required |
4,950 ÷ 305, rounded up |
17 boxes |
|
Order quantity |
Round to pricing tier |
20 boxes |
Verify the 90 metre permanent link limit for the furthest outlet before committing to a single rack position. If the furthest run exceeds it, either move the rack or add a second telecom room. Stretching a run past 90 metres is one of the errors covered in our guide to Cat6 installation mistakes that fail certification.
Ordering the full quantity in one go matters beyond price: cable from a single production run behaves consistently across the installation. Details on packing conventions are in our note on 305 metre boxes versus 1000 foot rolls.
|
Item |
Quantity |
Notes |
|---|---|---|
|
Cat6 UTP cable, 305 m box |
17–20 |
Bare copper, 23 AWG |
|
Cat6 keystone jacks |
110 |
100 + 10% spares |
|
Faceplates, single/dual gang |
50–100 |
Depends on outlets per plate |
|
Surface or flush back boxes |
50–100 |
Match faceplate count |
|
Cat6 patch panels, 24 port |
5 |
120 ports, spare capacity |
|
Patch cords, 1 m (rack side) |
110 |
Panel to switch |
|
Patch cords, 2–3 m (desk side) |
110 |
Outlet to device |
Patch cords are the line most often missed, and 200-plus cords is a material cost. They must be the same category as the cable — Cat5e cords on a Cat6 installation reduce the whole channel to Cat5e.
|
Item |
Quantity |
Notes |
|---|---|---|
|
42U floor standing rack |
1 |
800 mm deep minimum |
|
Horizontal cable managers, 1U |
5–6 |
One between panel pairs |
|
Vertical cable managers |
2 |
Both sides of rack |
|
Power distribution units |
2 |
Dual feed where available |
|
Rack shelves |
1–2 |
Non-rackmount equipment |
|
Rack fan tray |
1 |
Essential with PoE switches |
|
Earthing kit |
1 |
Rack bonding |
Rack space budget: 5U panels, 6U management, 3U switches, 2U UPS or PDU, 2U spare — roughly 18U used of 42U, leaving genuine growth room. Undersizing the rack is a false economy that surfaces at the first expansion.
|
Item |
Sizing basis |
|---|---|
|
Cable tray / basket |
Sized for full cable count at 40% fill |
|
Vertical risers |
Where cable changes level |
|
Conduit to outlets |
Drop from ceiling to back box |
|
Fire stopping |
Every fire compartment penetration |
|
Support and fixings |
Tray brackets, threaded rod, anchors |
Size containment at around 40 percent fill rather than capacity. A tray packed full cannot accept additions, and cables at the centre of a dense bundle cannot shed PoE heat. Fire stopping is frequently omitted from estimates and is not optional where cable crosses a fire compartment.
Velcro straps rather than nylon ties, labels and a labelling system, pulling lubricant for long runs, draw ropes, cable ties for temporary dressing only, and a certification field tester — usually hired rather than bought for a single project. Budget the tester and the time to use it; certification is what converts an installation into a warrantable one.
Indicative shares for a project of this size, useful for sanity checking a quotation:
|
Category |
Approx. share |
|---|---|
|
Labour |
35–45% |
|
Containment and fixings |
15–20% |
|
Cable |
10–15% |
|
Jacks, panels, patch cords |
10–15% |
|
Rack and management |
5–10% |
|
Testing and documentation |
3–5% |
The implication is worth stating: cable is a small share of the total. Downgrading cable specification to save money saves very little against the project while capping the installation's performance for its full service life. This is why apparent bargains in Cat6 pricing deserve scrutiny rather than enthusiasm.
Category. Cat6 for general office work; Cat6a where 10 Gigabit over full distance is required. Our category comparison covers the trade-offs.
Jacket. PVC as standard; LSZH where the fire strategy or specification requires it. See LSZH versus PVC.
Conductor. Solid bare copper, stated in writing on the quotation.
PoE load. Count the powered devices, size the switch budget accordingly, and limit bundle sizes on the affected runs.
Outdoor segments. Any run leaving the building needs outdoor rated cable and a grounding strategy.
A common planning ratio is two outlets per desk, which gives one for the workstation and one spare for a phone, printer or future device. Add outlets for wireless access points at roughly one per 1,000 square feet, plus points for printers, cameras, access control and meeting room equipment. A 100 desk office therefore often needs closer to 220 to 250 points, not 100.
At an average of 45 metres per run, 100 points needs about 4,500 metres. Adding 10 percent wastage brings it to roughly 4,950 metres, which is 17 boxes of 305 metres when rounded up. Adjust the average run length to suit your floor geometry and rack position.
Using standard 24 port patch panels, 100 points needs five panels, which gives 120 ports and leaves spare capacity. Allow one rack unit of cable management between each pair of panels, so the panels and management together occupy about 10 rack units.
Nakoda manufactures Cat6 UTP LAN cable in India with solid bare copper conductors, a central PVC spine and 250 MHz rating, supplied in 100 metre and 305 metre boxes.
Send us your point count, floor details and delivery city and we will confirm quantity and current pricing. Submit a bulk enquiry and our team will respond within one working day.